Question #: 589
Topic #: 59

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?


A.

Expedite the next phase to reduce slippage


B.

Add more float to the overall project schedule


C.

Request additional contingency from the sponsor.


D.

Organize a root cause analysis (RCA) workshop.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.