PMI Project Management Professional (PMBOK 7th Version) PMP Question # 590 Topic 60 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 590 Topic 60 Discussion

PMP Exam Topic 60 Question 590 Discussion:
Question #: 590
Topic #: 60

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?


A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.


B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.


C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.


D.

Change the meeting time to the working time zones of the stakeholders who are complaining.