PMI Project Management Professional (2025 Version) PMP Question # 586 Topic 59 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 586 Topic 59 Discussion

PMP Exam Topic 59 Question 586 Discussion:
Question #: 586
Topic #: 59

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?


A.

Ask stakeholders to communicate with the project manager and not directly with the team


B.

Empower the team members to remove obstacles and blockers


C.

Address and remove obstacles and blockers for the team


D.

Add blockers to the issue log and risk management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.