Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 586 Topic 59 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 586 Topic 59 Discussion

PMP Exam Topic 59 Question 586 Discussion:
Question #: 586
Topic #: 59

A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?


A.

Accept the change request from country A and reschedule the deployment project for country A.


B.

Take the request into account and ask the sponsor to inform countries B and C about the change


C.

Ask country A to submit a change request that will be analyzed along with countries B and C


D.

Refuse country As request as there is no time for the change as deployment has already begun


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.