PMI Project Management Professional (2025 Version) PMP Question # 587 Topic 59 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 587 Topic 59 Discussion

PMP Exam Topic 59 Question 587 Discussion:
Question #: 587
Topic #: 59

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?


A.

Update the issue log.


B.

Perform a qualitative risk analysis.


C.

Perform a root cause analysis.


D.

Implement a risk response plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.