Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 587 Topic 59 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 587 Topic 59 Discussion

PMP Exam Topic 59 Question 587 Discussion:
Question #: 587
Topic #: 59

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?


A.

Meet with each team member separately and apply an appropriate approach with each one.


B.

Approach the project sponsor and request help in discussing the project deliverables with team members.


C.

Explain to the team that the project manager is ultimately responsible for the delivery.


D.

Assign multiple managers to the various teams and delegate all of the tasks to them.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.