PMP Exam Topic 59 Question 587 Discussion:
Question #: 587
Topic #: 59

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?


A.

Monitor the interactions between the vendor and infrastructure manager going forward.


B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.


C.

Escalate the issue to the sponsor so appropriate action can be taken.


D.

Instruct the vendor to correct the problem without additional arguments.