PMI Project Management Professional (PMBOK 7th Version) PMP Question # 554 Topic 56 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 554 Topic 56 Discussion

PMP Exam Topic 56 Question 554 Discussion:
Question #: 554
Topic #: 56

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?


A.

Convinced the critical resource to remain on the project.


B.

Requested an experienced resource as a replacement


C.

Allocated additional time for mentoring


D.

Negotiated additional time to complete the project