PMP Exam Topic 56 Question 555 Discussion:
Question #: 555
Topic #: 56

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?


A.

Modify the daily standup meetings to include project status reporting.


B.

Escalate the issue to the change control board (CCB) and ask for advice.


C.

Adopt the role of supporting and empowering the project team to do the work.


D.

Change the approach for the project to a predictive approach.