PMI Project Management Professional (2025 Version) PMP Question # 555 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 555 Topic 56 Discussion

PMP Exam Topic 56 Question 555 Discussion:
Question #: 555
Topic #: 56

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?


A.

Risk log


B.

Change log


C.

Backlog


D.

Issue log


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.