New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 555 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 555 Topic 56 Discussion

PMP Exam Topic 56 Question 555 Discussion:
Question #: 555
Topic #: 56

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?


A.

Assess the business value impact and review the product roadmap to include any changes


B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously


C.

Stop the product release and start adding new user stones to the product backlog for any new requirements


D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.