Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 553 Topic 56 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 553 Topic 56 Discussion

PMP Exam Topic 56 Question 553 Discussion:
Question #: 553
Topic #: 56

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?


A.

Increase the sprint duration to allow the team more time


B.

Prioritize the contents of the backlog and remove some stories


C.

Create a change request to modify the gate review goals


D.

Use the standup meeting to assess impediments and problems


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.