PMI Project Management Professional (2025 Version) PMP Question # 553 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 553 Topic 56 Discussion

PMP Exam Topic 56 Question 553 Discussion:
Question #: 553
Topic #: 56

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?


A.

Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project


B.

Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes


C.

Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.


D.

Explain that distribution of important news can only be done using traceable communication methods


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.