PMI Project Management Professional (PMBOK 7th Version) PMP Question # 572 Topic 58 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 572 Topic 58 Discussion

PMP Exam Topic 58 Question 572 Discussion:
Question #: 572
Topic #: 58

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?


A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.


B.

Continue to work on the project until the stakeholders and management come to a decision.


C.

Socialize with the stakeholders to better understand their needs and reset expectations.


D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.