PMI Project Management Professional (2025 Version) PMP Question # 573 Topic 58 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 573 Topic 58 Discussion

PMP Exam Topic 58 Question 573 Discussion:
Question #: 573
Topic #: 58

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?


A.

Submit new user stories to the product owner in order to put documentation in the product backlog.


B.

Introduce a document management tool to support the agile teams in preparing the documentation.


C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.


D.

Add an additional team member to take up the role of scribe for the required documentation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.