Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 574 Topic 58 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 574 Topic 58 Discussion

PMP Exam Topic 58 Question 574 Discussion:
Question #: 574
Topic #: 58

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?


A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.


B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.


C.

Schedule a brainstorming session and select the top ten most important requirements.


D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.