PMP Exam Topic 58 Question 574 Discussion:
Question #: 574
Topic #: 58

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?


A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.


B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.


C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.


D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.