Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 594 Topic 60 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 594 Topic 60 Discussion

PMP Exam Topic 60 Question 594 Discussion:
Question #: 594
Topic #: 60

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?


A.

Propose using a compliance review board that will be responsible for approving allproduct features prior to their release to the public.


B.

Liaison with the compliance group, making them responsible for understanding therequirements and keeping them prioritized in the backlog.


C.

Meet with the compliance team and make sure that their requirements are covered in thedefinition of done (DoD) for each story.


D.

Ensure that the peer review process also covers compliance requirements, creating asecond layer of security for the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.