Question #: 593
Topic #: 60

A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.

What should the project manager do next?


A.

Extend the sprint timeline so the learn can work on the missing feature.


B.

Inform the product owner that this issue needs to be escalated to the executive level.


C.

Collaborate with the product owner and the team to plan the following sprint


D.

Initiate the change request process to include these missing features.