Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 593 Topic 60 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 593 Topic 60 Discussion

PMP Exam Topic 60 Question 593 Discussion:
Question #: 593
Topic #: 60

A labor union contract negotiation is delaying the completion of a project to build

a new manufacturing plant. Because the labor contract was due for renewal this year, the

project manager documented the negotiation process as a risk to the project. The project

was about to start the first phase of equipment installation at the plant when the negotiation began.

How should the project manager address the situation?


A.

Meet with the project team to determine options for risk mitigation.


B.

Log the issue and follow the planned actions in the risk response plan.


C.

Acquire contract resources and submit a change request for the cost impact.


D.

Escalate the issue to the steering committee to ask for mitigation support.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.