Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 557 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 557 Topic 56 Discussion

PMP Exam Topic 56 Question 557 Discussion:
Question #: 557
Topic #: 56

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?


A.

Developing new product lines


B.

Complying with new regulations


C.

Establishing company processes


D.

Certifying sustainable products


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.