PMP Exam Topic 56 Question 557 Discussion:
Question #: 557
Topic #: 56

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

PMP Question 557


A.

Continue with the sprint as the progress shows buffers for potential interruptions.


B.

Ask the product owner if some low-priority stories could be cut from the sprint.


C.

Continue with the sprint work as planned and keep monitoring.


D.

Ask the project team to select any additional stories as they have additional capacity than planned.