Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 598 Topic 60 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 598 Topic 60 Discussion

PMP Exam Topic 60 Question 598 Discussion:
Question #: 598
Topic #: 60

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?


A.

Start planning the project and then request that a PMO be implemented in the organization


B.

Request that the implementation of a PMO be executed in parallel with the project


C.

Provide project management training to only the internal team involved m the project


D.

Provide project management training to the stakeholders and explain their responsibilities


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.