PMI Project Management Professional (PMBOK 7th Version) PMP Question # 598 Topic 60 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 598 Topic 60 Discussion

PMP Exam Topic 60 Question 598 Discussion:
Question #: 598
Topic #: 60

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?


A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.


B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.


C.

Implement the role of an agile risk manager to take care of the risk management process.


D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.