PMP Exam Topic 60 Question 597 Discussion:
Question #: 597
Topic #: 60

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?


A.

Inform the steering committee of the situation and request additional resources.


B.

Coordinate virtual and face-to-face meetings at each site to improve communication


C.

Coordinate virtual meetings to assess the project team's communication needs


D.

Inform the project sponsor of this situation and request cultural orientation training.