PMI Project Management Professional (PMBOK 7th Version) PMP Question # 567 Topic 57 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 567 Topic 57 Discussion

PMP Exam Topic 57 Question 567 Discussion:
Question #: 567
Topic #: 57

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?


A.

Update the assumptions log and change log, and implement the change control process.


B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.


C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.


D.

Deliver what was planned in the project management document according to the specifications.