PMI Project Management Professional (2025 Version) PMP Question # 567 Topic 57 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 567 Topic 57 Discussion

PMP Exam Topic 57 Question 567 Discussion:
Question #: 567
Topic #: 57

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true''


A.

The project is on budget and on schedule.


B.

The project is over budget and behind schedule


C.

The project is under budget and behind schedule.


D.

The project is under budget and on schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.