Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 566 Topic 57 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 566 Topic 57 Discussion

PMP Exam Topic 57 Question 566 Discussion:
Question #: 566
Topic #: 57

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?


A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values


B.

Send a standard email to the team prior to every daily standup containing the new values


C.

Organize a team meeting focusing on the new values associated with the transformation


D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.