PMP Exam Topic 57 Question 565 Discussion:
Question #: 565
Topic #: 57

A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?


A.

Contact the functional managers to request substitutes for the conflicting team members.


B.

Send a warning to both team members indicating that if the issue continues, both will be removed from the project.


C.

Schedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.


D.

Escalate both team members to their respective functional managers and let them take the appropriate actions