During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?
A.
Review and update the project schedule according to performance
B.
Review the schedule baseline and consider adopting a schedule performance indicator
C.
Develop a lime. cost, and scope tracking method exclusively for this project.
D.
Adopt a formal change management process for the project
The project manager realizes that the project performance will be measured based on budget deviation and revenue, but without consideration for the overall project schedule. This could lead to a situation where the project is successful in terms of budget and revenue, but fails in terms of schedule. Therefore, the project manager should review the schedule baseline and consider adopting a schedule performance indicator. This will ensure that the project schedule is also taken into account when measuring project performance. References: PMBOK Guide, 6th Edition, Section 6.6.1.1, “Schedule Baseline” and Section 7.4.2.1, “Cost Performance Baseline”
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit