PMP Exam Topic 57 Question 565 Discussion:
Question #: 565
Topic #: 57

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?


A.

Review and update the project schedule according to performance


B.

Review the schedule baseline and consider adopting a schedule performance indicator


C.

Develop a lime. cost, and scope tracking method exclusively for this project.


D.

Adopt a formal change management process for the project