PMI Project Management Professional (2025 Version) PMP Question # 558 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 558 Topic 56 Discussion

PMP Exam Topic 56 Question 558 Discussion:
Question #: 558
Topic #: 56

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?


A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.


B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.


C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.


D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.