PMI Project Management Professional (2025 Version) PMP Question # 578 Topic 58 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 578 Topic 58 Discussion

PMP Exam Topic 58 Question 578 Discussion:
Question #: 578
Topic #: 58

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?


A.

Decompose the item immediately and begin work.


B.

Discuss the impact of starting the item with the team.


C.

Finish the small tasks in progress before decomposing the item.


D.

Communicate the impact with the project sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.