PMP Exam Topic 58 Question 575 Discussion:
Question #: 575
Topic #: 58

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?


A.

Update the issue log.


B.

Perform a qualitative risk analysis.


C.

Perform a root cause analysis.


D.

Implement a risk response plan.