Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 570 Topic 58 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 570 Topic 58 Discussion

PMP Exam Topic 58 Question 570 Discussion:
Question #: 570
Topic #: 58

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?


A.

Update the scope management plan to track the new government requirements.


B.

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.


C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.


D.

Request a change through the change control process to manage the new cybersecurityrequirements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.