PMI Project Management Professional (2025 Version) PMP Question # 464 Topic 47 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 464 Topic 47 Discussion

PMP Exam Topic 47 Question 464 Discussion:
Question #: 464
Topic #: 47

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?


A.

Update the stakeholder register.


B.

Refer to the resource management plan.


C.

Consult the project sponsor.


D.

Modify the statement of work (SOV).


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.