Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 464 Topic 47 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 464 Topic 47 Discussion

PMP Exam Topic 47 Question 464 Discussion:
Question #: 464
Topic #: 47

A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team

requests a change in the sprint goals and sprint backlog items.

What should the project manager do?


A.

Create a parallel sprint to deliver the additional items.


B.

Guide the agile team to add the new scope to the product backlog.


C.

Pause the sprint to allow time to include the new items.


D.

Moderate the expectations for sprint quality.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.