PMI Project Management Professional (PMBOK 7th Version) PMP Question # 465 Topic 47 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 465 Topic 47 Discussion

PMP Exam Topic 47 Question 465 Discussion:
Question #: 465
Topic #: 47

A project was recently flagged as being noncompliant during an inspection. Several options were suggested on how to address the noncompliance, but each may have different impacts on the budget, schedule, and quality.

How should the project manager proceed?


A.

Review the risk register.


B.

Perform a cost-benefit analysis.


C.

Determine the cost of change.


D.

Conduct a root cause analysis (RCA).