A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?


A.

Request the additional work through governance.


B.

Meet with the stakeholder and explain that additional work cannot be added.


C.

Prioritize the additional work in the backlog.


D.

Collaborate immediately with the stakeholder to complete the additional work.