PMI Project Management Professional (2025 Version) PMP Question # 462 Topic 47 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 462 Topic 47 Discussion

PMP Exam Topic 47 Question 462 Discussion:
Question #: 462
Topic #: 47

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?


A.

Change the project scope and seek approval to exclude this town from the overall

project.


B.

Engage with the town's authorities to discuss the reason for the change in commitment

and agree on a solution.


C.

Instruct the team to move to the next town and continue the project to avoid further delays.


D.

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.