A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?


A.

Circulated the project charter


B.

Assessed the organizational culture


C.

Determined the level of maturity of the employees


D.

Communicated the project schedule