Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 463 Topic 47 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 463 Topic 47 Discussion

PMP Exam Topic 47 Question 463 Discussion:
Question #: 463
Topic #: 47

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?


A.

Identified the stakeholders and their expectations


B.

Presented the project to the community


C.

Added this situation to the risk register


D.

Added these requests to the project scope statement


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.