Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 1 out of 12 pages
Viewing questions 1-50 out of questions
Questions # 1:

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?

Options:

A.

Align the project goals with the team member.


B.

Reassign the team member to another project.


C.

Nominate the team member to receive agile training.


D.

Allocate another resource to support the team member.


Expert Solution
Questions # 2:

A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two

projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.

What kind of leadership style should the project manager utilize for the current project?

Options:

A.

Transformational


B.

Interactional


C.

Laissez-faire


D.

Charismatic


Expert Solution
Questions # 3:

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?

Options:

A.

Facilitate a supportive level of engagement for this stakeholder.


B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.


C.

Perform a qualitative risk analysis using a probability and impact matrix.


D.

Ensure the key information is accurate and monitor the situation as the project progresses.


Expert Solution
Questions # 4:

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?

Options:

A.

Identified the vice president as a stakeholder


B.

Recorded the vice president's concerns in the risk register


C.

Escalated any dissent to top management right away


D.

Shared project boundaries so that everyone was aware of the scope


Expert Solution
Questions # 5:

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

    Update the issue log and refer to the resource management plan to address the situation.

    Ask the team for extra work to fulfill the project commitment.

    Reduce the scope of the project and inform stakeholders.

Options:

A.

Ask the sponsor for an experienced team member in the company to help the project team.


Expert Solution
Questions # 6:

A project team has two members with conflicting personalities. This is affecting the rest of the team's performance.

What should the project manager do?

Options:

A.

Understand the viewpoint of each team member.


B.

Organize a team-building activity for the team.


C.

Conduct an analysis to measure missed targets.


D.

Seek a solution during the daily coordination meeting.


Expert Solution
Questions # 7:

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Options:

A.

Ask the other project manager to change the delivery methodology.


B.

Request that the other project manager develop a work breakdown structure (WBS).


C.

Participate in the other project's daily standup meetings.


D.

Align with the other project manager's high-level project time lines.


Expert Solution
Questions # 8:

A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.

What should the project manager do?

Options:

A.

Hold separate retrospective meetings for both the vendor team and the internal team.


B.

Schedule a preliminary meeting with the account manager from the vendor and the test manager.


C.

Establish a clear agenda for the meeting and remind the vendor and internal teams that the scope is to improve the process.


D.

Invite the procurement manager and a representative from the vendor to manage the current tense relationship.


Expert Solution
Questions # 9:

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

Options:

A.

Reprioritize the backlog based on value and cost of delay divided by duration.


B.

Switch to a predictive approach to prevent any further delays to completion.


C.

Reprioritize the backlog based on story size and competence availability.


D.

Remove low-value items from the backlog to compensate for the higher cost.


Expert Solution
Questions # 10:

A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?

Options:

A.

Review the cost and schedule baselines for execution.


B.

Define change management for the new technology.


C.

Analyze the cost and identify the project benefits.


D.

Identify the risks in implementing the new technology.


Expert Solution
Questions # 11:

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?

Options:

A.

Requirements traceability matrix


B.

Risk management plan


C.

Project scope statement


D.

Requirements management plan


Expert Solution
Questions # 12:

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

Options:

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.


B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.


C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.


D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.


Expert Solution
Questions # 13:

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the

importance of this document to the project manager?

Options:

A.

Needed to close the work breakdown structure (WBS).


B.

Needed to share it with the stakeholders.


C.

Needed to close out the project or a phase.


D.

Needed to release the team at the end of the project.


Expert Solution
Questions # 14:

A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project

team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.

What should the project manager do?

Options:

A.

Discuss with the team, estimate the effort, and raise a change request.


B.

Discuss with the customer the risks identified and team's concerns.


C.

Ask the team to deliver the functionality on the agreed go-live date.


D.

Ask the customer to go live and add the new functionality in the backlog.


Expert Solution
Questions # 15:

During a project's execution phase, the team faced a setback in one of the deliveries and was asked to come up with a new plan. All team members joined a meeting to address the issue and, after a while, the project manager observed that two members of the team were just agreeing with anything that was proposed even though they were opposed to the outcome.

What conflict resolution style were the team members adopting?

Options:

A.

Avoidant style


B.

Combative style


C.

Collaborative style


D.

Accommodative style


Expert Solution
Questions # 16:

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to

evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4

months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the

following resources:

* Two engineers (monthly salary of US$700 each)

* One project manager (monthly salary of US$1,600)

* Additional estimated monthly expenses of US$2,000

The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house

resources.

How much money will the project manager estimate the company can save?

Options:

A.

US$35,000


B.

US$20,000


C.

US$40,000


D.

US$30,000


Expert Solution
Questions # 17:

A project manager is leading a diverse global team. The team members disagree about the requirements for a recently approved change request. The conflict among the team members has resulted in low morale and decreased performance.

What should the project manager do?

Options:

A.

Allow the most senior team member to make a decision and communicate the decision to the team members.


B.

Speak with the team members about their disagreement and seek clarity regarding the requirements.


C.

Ask for advice from the human resources (HR) department about how to handle the situation.


D.

Escalate to the change control board (CCB) and have them seek clarity on the requirements of the change.


Expert Solution
Questions # 18:

A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business. What should the project

manager do to ensure business value is delivered early?

Options:

A.

Create a detailed project plan and escalate delays to the functional managers.


B.

Fast track the project and monitor tasks closely to ensure timely delivery.


C.

Create robust incentives to the team members to encourage speedy delivery.


D.

Break down the deliverables into sprints and deliver value incrementally.


Expert Solution
Questions # 19:

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?

Options:

A.

Schedule a lessons learned meeting with the project team and close out the project.


B.

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.


C.

Prepare a transition plan to hand over the operations and other closing documentation.


D.

Document the project manager's departure and the missing documents in the risk log.


Expert Solution
Questions # 20:

A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.

What should the project manager do to manage such a situation for upcoming phases?

Options:

A.

Revise the project schedule to accommodate fixing discovered issues.


B.

Ensure customer validation occurs more frequently during the life cycle of the project.


C.

Review the customer validation team's test plan early in the life cycle.


D.

Ask the project team to increase unit testing of the deliverables.


Expert Solution
Questions # 21:

Eight highly qualified experts have been assembled to work for a 6-month period on an a specific aspect of an organization's product development process. How should the

project manager support this team to succeed?

Options:

A.

Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.


B.

Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.


C.

Define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.


D.

Work with the team members to define the overall objective and support them to engage around the goal.


Expert Solution
Questions # 22:

During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value. What should the

project manager do to address this concern?

Options:

A.

Review the project management plan tasks with the stakeholders.


B.

Review the project management plan budget with the stakeholders.


C.

Review the business benefits realization plan with the stakeholders.


D.

Review the communications management plan with the stakeholders,


Expert Solution
Questions # 23:

A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact

project implementation.

What should the project manager do next?

Options:

A.

Meet with the team member to understand their concerns and/or issues.


B.

Convene a team meeting to encourage and motivate the entire team.


C.

Assign an additional resource to help the team member with the tasks.


D.

Ask the team member's functional manager if there are any known issues.


Expert Solution
Questions # 24:

A company hired a new project lead to incorporate some agile practices.

Which three changes should the project lead incorporate in the existing team meetings? (Choose 3)

Options:

A.

Add sprints and sprint reviews as necessary.


B.

Agree with the team on some ground rules.


C.

Avoid extended discussions during daily meetings.


D.

Select a team member to lead the daily meetings.


E.

Encourage everyone to participate in the daily meetings.


Expert Solution
Questions # 25:

An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have

agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached.

Which approach should be used in this situation?

Options:

A.

A flow-based approach starting with the smallest stories.


B.

An iterative approach starting with the highest value epic.


C.

A predictive approach with short phases.


D.

An incremental approach with a minimum viable product (MVP).


Expert Solution
Questions # 26:

A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its

competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?

Options:

A.

Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step.


B.

Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays.


C.

Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step.


D.

Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.


Expert Solution
Questions # 27:

A project manager is asked to manage an agile project, allowing the company to comply with a new upcoming regulation. After the project kickoff, the scope is modified to have the project team work on specific tasks, while a global team will manage the program for several countries in parallel. The project management plan has not yet been shared, and the deadline to complete the project is fixed.

What should the project manager do to handle the scope change?

Options:

A.

Define an initial backlog and start working on the clearest tasks, then incrementally refine the scope.


B.

Create a risk entry in the risk management plan due to the lack of a global project management plan.


C.

Review the organizational process assets (OPAs) from past projects with similar scope changes.


D.

Formalize the change in the scope with the project sponsor to limit accountability for the specific tasks.


Expert Solution
Questions # 28:

Due to their different ideas regarding the execution of a project, a conflict has occurred between two stakeholders.

What should the project manager do to resolve the conflict?

Options:

A.

Arrange a group meeting with the stakeholders to generate creative alternatives.


B.

Address the conflict in a planned meeting with all stakeholders and project team members.


C.

Assess the conflict based upon the stakeholders' past disagreements.


D.

Focus on the personal issues between the stakeholders.


Expert Solution
Questions # 29:

A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,

Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.

What should the project manager do next?

Options:

A.

Perform a cost-benefit analysis to evaluate using the Point B option.


B.

Add the issue to the change log and request additional budget through the change control board (CCB).


C.

Seek a decision from the construction team after explaining the project budget and schedule constraint.


D.

Use the Point B option because it will save the project cost and time.


Expert Solution
Questions # 30:

A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses

predictive approaches, does not like virtual tools such as chats, task trackers, and so forth. They prefer email, telephone calls, and face-to-face

meetings.

How should the project manager approach this situation?

Options:

A.

Use regular screen-sharing sessions to show the progress to the stakeholder.


B.

Align and agree with the stakeholder on the communication approach.


C.

Ask the manager to use virtual communication tools and online dashboards.


D.

Create a digital dashboard to meet the manager's information needs.


Expert Solution
Questions # 31:

A project manager is building a team to work on a service integration project that will transition technology management services from company A to company B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, have different types of technology backgrounds, and use different approaches for work.

How should the project manager build a cohesive, high-performing team?

Options:

A.

Organize the team members into several kick-off sessions based on technology type.


B.

Review the list of team members’ skills and understand how they will work together to deliver the project outcomes.


C.

Ask the human resources (HR) department to arrange interview meetings to select the team.


D.

Ask prospective team members to write a short biography explaining how they can contribute to the team's success.


Expert Solution
Questions # 32:

An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.

What should the project manager do first?

Options:

A.

Review the risk register and assign functional managers as resources.


B.

Analyze the resource pool and assign internal resources who participated in past projects.


C.

Perform an analysis of the key cost drivers and present alternatives.


D.

Review the work breakdown structure (WBS) to ensure there are adequate resources.


Expert Solution
Questions # 33:

A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?

Options:

A.

Suggest that the team member contact the IT department.


B.

Facilitate a priority resolution of the issue with the IT department.


C.

Update the issue log and escalate the problem to the product owner.


D.

Ask the other team members to step in and do the work.


Expert Solution
Questions # 34:

A project manager holds periodic progress review meetings to discuss issues. What should the project manager do first on the agenda?

Options:

A.

Produce lessons learned documentation.


B.

Elaborate the risk mitigation strategy and risk register.


C.

Formulate project management plan integration.


D.

Update resolution approaches and action assignments.


Expert Solution
Questions # 35:

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?

Options:

A.

Invite the director to attend the daily standup meetings.


B.

Share this with the team and ask them to develop reports for the director.


C.

Introduce the agile aspect to the director and agree on a solution.


D.

Explain to the director that agile projects have live reports.


Expert Solution
Questions # 36:

An organization's human resources (HR) department wants to create a high-performing team and implement a project that includes job grading, organizational restructuring, and soft skills training.

To ensure the quality of the project deliverable, which three actions should the project manager take? (Choose 3)

Options:

A.

Collect feedback and conduct surveys and questionnaires.


B.

Hire a certified expert to lead the project quality process.


C.

Document quality gaps and analyze them for continuous improvement.


D.

Develop a proper quality management plan with measurable metrics.


E.

Apply an existing external framework for performance improvement.


Expert Solution
Questions # 37:

A project manager is leading a project that is kicking off next month. The project manager realizes that there are many stakeholders that need updates on different aspects of the project at different frequencies.

What should the project manager do first to ensure each stakeholder has the information they need?

Options:

A.

Develop a communications management plan that reflects the needs of the stakeholder community.


B.

Engage with each stakeholder to determine their information needs related to the project.


C.

Create a responsible, accountable, consulted, and informed (RACI) chart based on the stakeholders and their communications needs.


D.

Determine the most appropriate mechanisms to leverage when communications are necessary.


Expert Solution
Questions # 38:

A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.

What should the project manager do first?

Options:

A.

Review the project schedule and ask for the contingency reserve to crash the project.


B.

Meet the project team and stakeholders to identify the root cause of the issue and develop a solution.


C.

Review the lessons learned register with the former project manager in a private meeting.


D.

Meet the project team to assert authority and reassign the project tasks for a timely delivery.


Expert Solution
Questions # 39:

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

Options:

A.

Develop a more comprehensive template for the definition of done (DoD).


B.

Increase the percentage allocated for testing each backlog item.


C.

Organize more frequent sprint reviews with a broader audience.


D.

Establish a quality assurance (QA) team separate from the development team.


Expert Solution
Questions # 40:

A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise.

Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)

Options:

A.

Arrange a daily learning session for project team members during lunch to facilitate knowledge transfer.


B.

Allow each team member time in the retrospective sessions to share a little bit about their role and areas of knowledge.


C.

Assess the gaps and assign an expert resource for respective areas of knowledge.


D.

Identify external subject matter experts (SMEs) and plan training sessions to conduct knowledge transfer.


E.

Schedule shadowing sessions among team members to facilitate team learning.


Expert Solution
Questions # 41:

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

Options:

A.

Ensure that the schedule is aligned with the vision and objectives.


B.

Escalate the compliance issue to the project management office (PMO).


C.

Congratulate the team and move on to the execution phase.


D.

Develop a new detailed schedule with the team and project sponsor.


Expert Solution
Questions # 42:

A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action.

What should the project manager do to avoid similar complaints?

Options:

A.

Present the status at a weekly meeting with the steering committee.


B.

Verify the information needed for steering committee members.


C.

Send a shorter daily report to this steering committee member.


D.

Demonstrate the weekly reports in a presentation for the steering committee member.


Expert Solution
Questions # 43:

A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?

Options:

A.

Talk to the team member to determine why their performance changed.


B.

Talk to the team member and a human resources (HR) representative.


C.

Talk to the team member's manager to provide more training.


D.

Talk to the project lead and ask them to allocate less demanding tasks.


Expert Solution
Questions # 44:

A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?

Options:

A.

Request the additional work through governance.


B.

Meet with the stakeholder and explain that additional work cannot be added.


C.

Prioritize the additional work in the backlog.


D.

Collaborate immediately with the stakeholder to complete the additional work.


Expert Solution
Questions # 45:

A large multi-national company works on a project in an emerging-economy country. All business matters are conducted in local currency. During the course of the project,

the budget becomes the primary concern due to currency instability in the country.

What should the project manager do next?

Options:

A.

Evaluate the situation with the team


B.

Escalate the risk to the project sponsor


C.

Use the project's contingency reserve


D.

Ask for additional budget from the client


Expert Solution
Questions # 46:

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?

Options:

A.

Have the team complete the technically complex story first.


B.

Work with the product owner to clarify and prioritize the backlog stories.


C.

Have the team complete the less complex story first.


D.

Work with the agile coach on the user stories to avoid conflict.


Expert Solution
Questions # 47:

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

Options:

A.

Business Documentation


B.

Stakeholder Register


C.

Risk Register


D.

Project Charter


Expert Solution
Questions # 48:

While reviewing a project with high-level executives, the project manager realizes that the conversation always deviates to other topics instead of the project itself.

What two actions should the project manager take? (Choose 2)

Options:

A.

Review with the team all of the topics that came up during the meeting.


B.

Extend the meeting time to review additional topics.


C.

Redirect the conversation to the project updates.


D.

Restrict offline reviews to critical points related to the project.


E.

Schedule effective communications training for the stakeholders.


Expert Solution
Questions # 49:

A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value.

What should the project manager have done differently?

Options:

A.

Invited the customer to the daily meetings


B.

Helped the team redefine the MVP


C.

Changed the duration of iterations to deliver more value


D.

Validated the iteration goals with the customer


Expert Solution
Questions # 50:

A project manager has expertise in the technical domain. The project manager frequently demonstrates unacceptable behavior toward other team

members; however, when confronted, the project manager denies this behavior.

What is the reason for the project manager's behavior?

Options:

A.

The project manager lacks necessary empathy.


B.

The project manager lacks emotional intelligence (El).


C.

The project manager was not properly trained.


D.

The project manager is in the wrong project role.


Expert Solution
Viewing page 1 out of 12 pages
Viewing questions 1-50 out of questions