A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?
Match each dimension of the communications management plan to its corresponding focus.
What scenario describes when a project must be created due to market demand?
Which of the following is a category of organizational process assets?
What should a project manager use to determine how much money is needed to complete a project?
A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?
Which set of activities should a project manager use as part of the Develop Team process?
What are the key tools for managing project knowledge?
A team receives four different requests from separate stakeholders related to one application Match each requirement with its corresponding type of change request.
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
How should a project manager plan communication for a project which has uncertain requirements?
Creating the project scope statement is part of which process?
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
Which of the following are processes associated with Project Cost Management?
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
According to the PMI Talent Triangle. leadership skills relate to the ability to:
Which action should the project manager take after the team finishes executing the scope?
A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?
The Agile principle "welcome changing requirement, even late in development" relates to which agile manifesto?
Which Manage Communications tool or technique focuses on identifying and managing barriers?
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:
Which item is a cost of conformance?
The purpose of the Project Communications Management Knowledge Area is to:
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
The following is a network diagram for a project.
The total float for the project is how many days?
A graphic display of project team members and their reporting relationships is known as a:
Which Process Group includes the Manage Stakeholder Engagement process?
One of the key benefits of the Plan Human Resource Management process is that it:
Which items are an output of the Perform Integrated Change Control process?
Which type of organizational structure is displayed in the diagram provided?
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
Outputs of the Control Communications process include:
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
Which type of graphic is displayed below?
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
Project Stakeholder Management focuses on:
The process of defining how the project scope will be validated and controlled is known as:
Which project document is updated in the Control Stakeholder Engagement process?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
In complex projects/ initiating processes should be completed:
A tool and technique used in the Develop Project Charter process is:
Specification of both the deliverables and the processes is the focus of: