If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
An output of the Create WBS process is:
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
In an organization with a projectized organizational structure, who controls the project budget?
The stakeholder register is an output of:
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
A project management office manages a number of aspects including the:
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
The procurement process that documents agreements and related documentation for future reference is known as:
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
When would resource leveling be applied to a schedule model?
Which of the following is a tool and technique for Estimate Activity Durations?
Which action should a project manager take to ensure that the project management plan is effective and current?
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
The links between the processes in the Process Groups are often:
Cost baseline is an output of which of the following processes?
Which of the following processes are part of the Project Integration Management Knowledge Area?
What is the difference between the critical path and the critical chain?
Which of the following is contained within the communications management plan?
Who selects the appropriate processes for a project?
A procurement management plan is a subsidiary of which other type of plan?
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
Which defines the portion of work included in a contract for items being purchased or acquired?
Taking out insurance in relation to risk management is called what?
Outputs of the Control Communications process include:
The process of formalizing acceptance of the completed project deliverables is known as:
Plan Risk Management is the process of defining how to:
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
An input required in Define Scope is an organizational:
Which process is included in the Project Integration Management Knowledge Area?
Projects are undertaken by an organization to support the:
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
The individual or group that provides resources and support for a project and is accountable for success is the:
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
Which schedule network analysis technique modifies the project schedule to account for limited resources?
An input of the Control Schedule process is the:
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
During which process group is the quality policy determined?
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
Which of the following is an output of the Monitor and Control Project Work process?
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?