Questions # 251:

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition


B.

Modeling techniques


C.

Resource optimization


D.

Meetings


Expert Solution
Questions # 252:

The ability to influence cost is greatest during which stages of the project?

Options:

A.

Early


B.

Middle


C.

Late


D.

Completion


Expert Solution
Questions # 253:

An output of the Plan Quality Management process is:

Options:

A.

A process improvement plan,


B.

Quality control measurements.


C.

Work performance information,


D.

The project management plan.


Expert Solution
Questions # 254:

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing


B.

Initiating


C.

Planning


D.

Monitoring and Controlling


Expert Solution
Questions # 255:

The Monitoring and Controlling Process Group includes processes that:

Options:

A.

Establish the scope, objectives, and course of action of a project,


B.

Define a new project or a new phase of an existing project.


C.

Track, review, and regulate the progress and performance of a project.


D.

Complete the work defined in the project management plan.


Expert Solution
Questions # 256:

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.


B.

Acquire Project Team.


C.

Manage Project Team.


D.

Develop Project Team.


Expert Solution
Questions # 257:

Which item is a formal proposal to modify any document, deliverable, or baseline?

Options:

A.

Change request


B.

Requirements documentation


C.

Scope baseline


D.

Risk urgency assessment


Expert Solution
Questions # 258:

An input to the Manage Project Team process is:

Options:

A.

Work performance reports.


B.

Change requests.


C.

Activity resource requirements.


D.

Enterprise environmental factors.


Expert Solution
Questions # 259:

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)


B.

Cost performance index (CPI)


C.

Budget at completion (BAC)


D.

Variance at completion (VAC)


Expert Solution
Questions # 260:

Which grid shows which resources are tied to work packages?

Options:

A.

Work breakdown structure (WBS)


B.

Responsibility assignment matrix (RAM)


C.

Project assignment chart


D.

Personnel assignment matrix


Expert Solution
Questions # 261:

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

Options:

A.

Force/direct


B.

Withdraw/avoid


C.

Compromise/reconcile


D.

Collaborate/problem solve


Expert Solution
Questions # 262:

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work


B.

Perform Quality Assurance


C.

Close Project or Phase


D.

Control Scope


Expert Solution
Questions # 263:

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,


B.

Final products or services,


C.

Document updates,


D.

Work performance information.


Expert Solution
Questions # 264:

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

Options:

A.

Collect Requirements.


B.

Conduct Procurements.


C.

Estimate Activity Durations.


D.

Estimate Activity Resources.


Expert Solution
Questions # 265:

Which Control Quality tool is also known as an arrow diagram?

Options:

A.

Matrix diagram


B.

Affinity diagram


C.

Tree diagram


D.

Activity network diagram


Expert Solution
Questions # 266:

Risk categorization is a tool or technique used in which process?

Options:

A.

Plan Risk Responses


B.

Plan Risk Management


C.

Perform Qualitative Risk Analysis


D.

Perform Quantitative Risk Analysis


Expert Solution
Questions # 267:

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Options:

A.

Organizational process updates


B.

Quality metrics


C.

Change requests


D.

Quality control measurements


Expert Solution
Questions # 268:

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

Options:

A.

Control charts


B.

Pareto diagrams


C.

Ishikavva diagrams


D.

Checksheets


Expert Solution
Questions # 269:

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication


B.

Claims administration


C.

Conflict management


D.

Performance reporting


Expert Solution
Questions # 270:

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

Options:

A.

Direct and Manage Project Work


B.

Develop Project Management Plan


C.

Plan Quality Management


D.

Monitor and Control Project Work


Expert Solution
Questions # 271:

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Options:

A.

Requirements documentation


B.

Requirements traceability matrix


C.

Project management plan updates


D.

Project documents updates


Expert Solution
Questions # 272:

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient


B.

Effective


C.

Push


D.

Pull


Expert Solution
Questions # 273:

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

Options:

A.

Customers.


B.

Business partners.


C.

Sellers.


D.

Functional managers.


Expert Solution
Questions # 274:

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan


B.

Stakeholder register


C.

Risk log


D.

Communications management plan


Expert Solution
Questions # 275:

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning


B.

At the beginning and the end


C.

Once during each phase


D.

Repeatedly


Expert Solution
Questions # 276:

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work


B.

Purchase order


C.

Source selection criteria


D.

Bidder conference


Expert Solution
Questions # 277:

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

Options:

A.

Human resource management plan.


B.

Activity resource requirements.


C.

Personnel assessment tools,


D.

Multi-criteria decision analysis.


Expert Solution
Questions # 278:

A large portion of a projects budget is typically expended on the processes in which Process Group?

Options:

A.

Executing


B.

Planning


C.

Monitoring and Controlling


D.

Closing


Expert Solution
Questions # 279:

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

Options:

A.

Cost management plan.


B.

Work performance information.


C.

Quality management plan.


D.

Work breakdown structure.


Expert Solution
Questions # 280:

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Options:

A.

Procurement documents


B.

Communications plan


C.

Project charter


D.

Stakeholder register


Expert Solution
Questions # 281:

In the Plan Stakeholder Management process, expert judgment is used to:

Options:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.


B.

Ensure comprehensive identification and listing of new stakeholders.


C.

Analyze the information needed to develop the project scope statement.


D.

Decide the level of engagement of the stakeholders at each required stage.


Expert Solution
Questions # 282:

The Perform Integrated Change Control process occurs in which Process Group?

Options:

A.

Initiating


B.

Executing


C.

Monitoring and Controlling


D.

Planning


Expert Solution
Questions # 283:

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Options:

A.

Continuous improvement.


B.

Predictive planning.


C.

Progressive elaboration.


D.

Quality assurance.


Expert Solution
Questions # 284:

An input to Conduct Procurements is:

Options:

A.

Independent estimates.


B.

Selected sellers.


C.

Seller proposals.


D.

Resource calendars.


Expert Solution
Questions # 285:

An element of the project scope statement is:

Options:

A.

Acceptance criteria.


B.

A stakeholder list.


C.

A summary budget,


D.

High-level risks.


Expert Solution
Questions # 286:

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:

A.

event.


B.

response,


C.

perception.


D.

impact.


Expert Solution
Questions # 287:

Prototype development may be used as a tool for which of the following risk response strategies?

Options:

A.

Avoid


B.

Accept


C.

Mitigate


D.

Exploit


Expert Solution
Questions # 288:

The initial development of a Project Scope Management plan uses which technique?

Options:

A.

Alternatives identification


B.

Scope decomposition


C.

Expert judgment


D.

Product analysis


Expert Solution
Questions # 289:

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis


B.

Three-point estimating


C.

Parametric estimating


D.

Analogous estimating


Expert Solution
Questions # 290:

An input of the Create WBS process is:

Options:

A.

requirements documentation.


B.

scope baseline.


C.

project charter.


D.

validated deliverables.


Expert Solution
Questions # 291:

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:

A.

Corrective action


B.

Defect repair


C.

Preventative action


D.

Probable action


Expert Solution
Questions # 292:

Which of the following response strategies are appropriate for negative risks or threats?

Options:

A.

Share, Accept, Transfer, or Mitigate


B.

Exploit, Enhance, Share, or Accept


C.

Mitigate, Share, Avoid, or Accept


D.

Avoid, Mitigate, Transfer, or Accept


Expert Solution
Questions # 293:

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Options:

A.

0.8


B.

0.89


C.

1.13


D.

1.25


Expert Solution
Questions # 294:

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).


B.

Cost Plus Fixed Fee Contract (CPFF).


C.

Fixed Price Incentive Fee Contract (FPIF).


D.

Time and Material Contract (T&M).


Expert Solution
Questions # 295:

A tool and technique used during the Define Scope process is:

Options:

A.

facilitated workshops.


B.

observations.


C.

questionnaires and surveys.


D.

group creativity techniques.


Expert Solution
Questions # 296:

One of the objectives of a quality audit is to:

Options:

A.

highlight the need for root cause analysis.


B.

share the process documentation among stakeholders.


C.

offer assistance with non-value-added activities.


D.

identify all of the gaps or shortcomings.


Expert Solution
Questions # 297:

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two


B.

Four


C.

Five


D.

Twelve


Expert Solution
Questions # 298:

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating


B.

Planning


C.

Executing


D.

Monitoring and Controlling


Expert Solution
Questions # 299:

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis


B.

Define Scope


C.

Verify Scope


D.

Control Scope


Expert Solution
Questions # 300:

Which statement correctly describes the value of a business case?

Options:

A.

It provides the necessary information to determine if a project is worth the required investment.


B.

It provides for alternative dispute resolution procedures in event of contract default.


C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.


D.

It is used to help a project manager understand the scope of commercial advantages.


Expert Solution
Viewing page 6 out of 8 pages
Viewing questions 251-300 out of questions