Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 5 out of 9 pages
Viewing questions 41-50 out of questions
Questions # 41:

During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.

What should the risk manager do to address the new risk of increased logistics costs?

Options:

A.

Accept the increased costs as part of the project ' s risk threshold.


B.

Develop a contingency plan to cover additional logistics expenses.


C.

Switch suppliers to potentially reduce logistics expenses.


D.

Incorporate a cost-sharing arrangement with the suppliers.


Expert Solution
Questions # 42:

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

Options:

A.

Review and revise the strategies periodically.


B.

Implement the strategies after completing the risk analysis.


C.

Implement the strategies immediately.


D.

Ensure the strategies are approved by the stakeholders.


Expert Solution
Questions # 43:

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.


B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.


C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.


D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.


Expert Solution
Questions # 44:

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.

Update the risk register


B.

Meet with the project ' s stakeholders


C.

Revise the risk management plan


D.

Ensure sufficient resources are available


Expert Solution
Questions # 45:

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.

Request for a skilled facilitator to help resolve conflicts that have arise.


B.

Refer to the team’s ground rules on how to resolve conflicts.


C.

Run a sensitivity analysis to check which risks have the most impact.


D.

Use the assumption analysis techniques to validate the assumptions.


Expert Solution
Questions # 46:

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board ' s response?

Options:

A.

Engaging the key stakeholders during the prioritization process


B.

Prioritizing the risks based on the project sponsor ' s risk appetite


C.

Engaging with the project sponsor before presenting to the board


D.

Working with an established industry standard prioritization method


Expert Solution
Questions # 47:

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

Options:

A.

Ask the sponsor to define the risk strategy to align with client needs.


B.

Develop a framework and engage the team in creating a risk plan.


C.

Train the team on basic techniques and defer the risk strategy for later.


D.

Concentrate on high-priority risks to meet the sponsor ' s expectations.


Expert Solution
Questions # 48:

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.


B.

Assess and modify the project risk management plan in response to the new directive.


C.

Accept project risks since it is already within the enterprise-wide threshold.


D.

Advise that the decision could increase the risk of their portfolio exponentially.


Expert Solution
Questions # 49:

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.


B.

Use the Wideband Delphi method.


C.

Use the brainstorming technique.


D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 


Expert Solution
Questions # 50:

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization


B.

The risk simul-ation


C.

The full risk description


D.

The risk response plan


Expert Solution
Viewing page 5 out of 9 pages
Viewing questions 41-50 out of questions