Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 5 out of 9 pages
Viewing questions 41-50 out of questions
Questions # 41:

The project manager leading a company ' s digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.


B.

The organization ' s professional engineers having reservations about possible information tampering.


C.

A growing number of competitors with digital signatures.


D.

An elimination of manual steps associated with recording wet signatures


E.

The growing adoption of mobile communications in the industry.


Expert Solution
Questions # 42:

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Options:

A.

Reformed the risk monitoring and closing process properly.


B.

Created the project work plan and budget more accurately.


C.

Educated the project team on budget change requests.


D.

Communicated better with the organization ' s CEO.


Expert Solution
Questions # 43:

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.

Perform a qualitative risk analysis and update the results.


B.

Update the assumptions/exclusions register with the new information.


C.

Update the risk register and prepare for the Monte Carlo analysis.


D.

Perform a quantitative risk analysis and update the results.


Expert Solution
Questions # 44:

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.


B.

Use the Wideband Delphi method.


C.

Use the brainstorming technique.


D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 


Expert Solution
Questions # 45:

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Options:

A.

Combine individual and focus groups to identify risks and create the overall risk register.


B.

Use focus groups to conduct group risk assessments of the project to identify risks.


C.

Request individual assessments of the project and its deliverables to identify risks.


D.

Use the external risk assessment of the project and its deliverables to identify risks.


Expert Solution
Questions # 46:

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.

Conduct a subject matter expert (SME) meeting.


B.

Perform qualitative analysis.


C.

Prioritize after quantitative analysis


D.

Prioritize the stakeholders affected.


Expert Solution
Questions # 47:

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

Options:

A.

Escalate the problem to the project sponsors.


B.

Execute the approved risk response plan.


C.

Negotiate with the supplier to resolve the problem.


D.

Assign a team member to update the issue leg.


Expert Solution
Questions # 48:

A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.

What should the risk manager do?

Options:

A.

Develop risk assessment processes and tools to quantify risk thresholds.


B.

Work with stakeholders to achieve consensus on risk thresholds.


C.

Use subject matter experts and historical data to estimate risk thresholds.


D.

Review regulatory requirements and the contract to identify risk thresholds.


Expert Solution
Questions # 49:

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

Options:

A.

Establish a formal and upfront risk identification process.


B.

Use a detailed and quantitative risk assessment process.


C.

Create an effective and clear risk communication process.


D.

Adopt a dynamic and frequent risk management process.


Expert Solution
Questions # 50:

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.


B.

Develop risk response plans for all identified risks.


C.

Update the communications management plan to avoid future issues


D.

Monitor and control secondary and residual risks in the risk register.


Expert Solution
Viewing page 5 out of 9 pages
Viewing questions 41-50 out of questions