PMI-RMP Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board ' s response?


A.

Engaging the key stakeholders during the prioritization process


B.

Prioritizing the risks based on the project sponsor ' s risk appetite


C.

Engaging with the project sponsor before presenting to the board


D.

Working with an established industry standard prioritization method