Pre-Winter Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 48 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 48 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

A project manager is leading a complex, high-risk construction project in the city center. To address risk based on lessons learned from similar past building projects, the risk manager assigns a team member to assess and confirm risk thresholds for the project.

What should the risk manager do?


A.

Develop risk assessment processes and tools to quantify risk thresholds.


B.

Work with stakeholders to achieve consensus on risk thresholds.


C.

Use subject matter experts and historical data to estimate risk thresholds.


D.

Review regulatory requirements and the contract to identify risk thresholds.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.