PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 48 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 48 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?


A.

Earned value management (EVM) variance metrics


B.

A risk burndown chart showing remaining risks


C.

The format established in the risk management plan


D.

An itemized list of remaining risks and their scores 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.