PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 49 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 49 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X's project manager avoid this situation in the future?


A.

Prepare a contingency response plan to implement when delays occur


B.

Ask the other project manager to officially confirm the new date in writing


C.

Request that the other project manager be added to relevant reports


D.

Request that the other project manager inform if any additional delays are expected


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.