Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 1 out of 7 pages
Viewing questions 1-10 out of questions
Questions # 1:

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.

Update the new risk in the risk register.


B.

Plan responses for the new risk.


C.

Passively accept the new risk.


D.

Add the new risk to the watch list.


Expert Solution
Questions # 2:

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.

Risk description risk response, and quantitative data


B.

Project plan, risk complexity, and secondary risk


C.

Project plan, risk priority, and tool availability


D.

Risk description, risk probability, and risk impact 


Expert Solution
Questions # 3:

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders'?

Options:

A.

Monte Carlo analysis


B.

Pareto analysis


C.

Ishikawa analysis


D.

Qualitative risk analysis


Expert Solution
Questions # 4:

in a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?

Options:

A.

Work breakdown structure (WBS)


B.

Affinity diagram


C.

Monte Carlo simul-ation


D.

Mind mapping


Expert Solution
Questions # 5:

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

Options:

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis


B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis


C.

Decision tree analysis


D.

Cost-benefit analysis


Expert Solution
Questions # 6:

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

How should the project manager handle stakeholder expectations?

Options:

A.

Add buffers to the schedule to accommodate risk.


B.

Ensure the risk register includes all identified risks.


C.

Discuss the risk response strategies with the stakeholders.


D.

Develop a communication plan to share updates on risks.


Expert Solution
Questions # 7:

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

Options:

A.

Import a risk register from other industry chemical laboratories.


B.

Define chemical laboratory safety risk thresholds.


C.

Review published operational experience reports.


D.

Draft threat and opportunity risks that come to mind.


Expert Solution
Questions # 8:

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Options:

A.

Engaged the sponsor and informed them of the decision to remove the planned feature.


B.

Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.


C.

Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.


D.

Created a schedule buffer in the plan to deal with unknown risks if and when they occurred. 


Expert Solution
Questions # 9:

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.


B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.


C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.


D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account. 


Expert Solution
Questions # 10:

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

Options:

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.


B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.


C.

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.


D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.


Expert Solution
Viewing page 1 out of 7 pages
Viewing questions 1-10 out of questions