Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 1 out of 9 pages
Viewing questions 1-10 out of questions
Questions # 1:

A risk manager is preparing the risk strategy for a strategic project, which involves stakeholders based in multiple locations. What should the risk manager do at this stage?

Options:

A.

Update the risk communications plan to include all stakeholders.


B.

Define the risk processes and tools to be adopted.


C.

Update the risk register to include this stakeholder-related risk.


D.

Refine the risk assumptions and criteria to be used.


Expert Solution
Questions # 2:

A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

What is an effect of adding the correlation to the model?

Options:

A.

Allows more risks to be included in the model.


B.

Reduces the project completion duration.


C.

Increases the standard deviation of the model.


D.

Increases the probability of correlated activities finishing on time.


Expert Solution
Questions # 3:

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.

Update the new risk in the risk register.


B.

Plan responses for the new risk.


C.

Passively accept the new risk.


D.

Add the new risk to the watch list.


Expert Solution
Questions # 4:

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Options:

A.

Scenario-based risk analysis


B.

Quantitative risk analysis


C.

Qualitative risk analysis


D.

Monte Carlo analysis 


Expert Solution
Questions # 5:

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.


B.

Implement the risk response plan.


C.

Implement the risk contingency plan.


D.

Communicate the identified residual risk.


Expert Solution
Questions # 6:

A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.

What should the risk manager do?

Options:

A.

Study the change logs to implement the approved change requests.


B.

Close out the expired risk and update the relevant project documents.


C.

Get permission from stakeholders before documenting lessons learned.


D.

Continue monitoring the critical response plan on the delivered product.


Expert Solution
Questions # 7:

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

Options:

A.

Project contracts


B.

Lessons learned registers from analogous projects


C.

Risk register


D.

Risk management plan


E.

Code of regulations


Expert Solution
Questions # 8:

The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team ' s approach to risk reports?

Options:

A.

Talk to the project team and ensure they avoid direct communication with this stakeholder.


B.

Engage with the team to enhance the project risk reports sent to the stakeholders.


C.

Highlight to the stakeholders the agreed predetermined frequency of risk reports.


D.

Work with the project sponsor to ensure stakeholders avoid directly influencing the project team.


Expert Solution
Questions # 9:

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

Options:

A.

Risk thresholds


B.

Risk response strategies


C.

Risk management reports


D.

Risk breakdown structure (RBS)


Expert Solution
Questions # 10:

When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?

Options:

A.

During the Plan Risk Management process


B.

Once all individual risks have been scored


C.

After risks have been identified by stakeholders


D.

Once the overall project risk has been estimated


Expert Solution
Viewing page 1 out of 9 pages
Viewing questions 1-10 out of questions