Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 1 out of 9 pages
Viewing questions 1-10 out of questions
Questions # 1:

A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.

Which approach should the risk manager take to improve the quality of the project risk analysis?

Options:

A.

Use brainstorming to identify more possible risks.


B.

Use a Monte Carlo simulation to identify risks.


C.

Use a work breakdown structure (WBS) to help analyze risks.


D.

Use a qualitative or quantitative analysis to analyze identified risks.


Expert Solution
Questions # 2:

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.

Close and communicate the results of the risk response actions.


B.

Run a workshop to analyze the effectiveness of the risk plan.


C.

Conduct a risk reserve analysis and document the results.


D.

Verify that all risk response actions have been documented. 


Expert Solution
Questions # 3:

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

Options:

A.

Put the risk on the watch list.


B.

Seek guidance from subject matter experts (SMEs).


C.

Ignore this risk as it is not critical.


D.

Inform the stakeholders about this risk.


Expert Solution
Questions # 4:

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

Options:

A.

To enable the team in identifying the specific causes of risks associated with project objectives.


B.

To ensure that project priorities are being appropriately factored into risk response plans.


C.

To determine there more attentive project leadership and organizational involvement is needed.


D.

To assign risks and risk severities to functional discipline and departments effectively.


Expert Solution
Questions # 5:

Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded


B.

When the stakeholders agree a risk is no longer applicable


C.

When the risk has been realized and can no longer happen again


D.

When iterative data analysis determines the risk is not applicable


Expert Solution
Questions # 6:

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.


B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.


C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.


D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.


Expert Solution
Questions # 7:

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).

How many total story points is the entire initiative?

Options:

A.

72


B.

60


C.

40


D.

32


Expert Solution
Questions # 8:

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.

Sensitivity analysis


B.

What-if scenario analysis


C.

Regression analysis


D.

Decision tree analysis


Expert Solution
Questions # 9:

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board ' s response?

Options:

A.

Engaging the key stakeholders during the prioritization process


B.

Prioritizing the risks based on the project sponsor ' s risk appetite


C.

Engaging with the project sponsor before presenting to the board


D.

Working with an established industry standard prioritization method


Expert Solution
Questions # 10:

The risk manager for a large-scale software development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor requests that the risk manager identify and address any potential risks that could disrupt project delivery.

What should the risk manager do?

Options:

A.

Create a list of potential issues.


B.

Consult the project management plan.


C.

Conduct risk management exercises.


D.

Perform qualitative risk analysis.


Expert Solution
Viewing page 1 out of 9 pages
Viewing questions 1-10 out of questions