Question #: 9
Topic #: 1

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?


A.

Risk thresholds


B.

Risk response strategies


C.

Risk management reports


D.

Risk breakdown structure (RBS)