PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 36 Topic 4 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 36 Topic 4 Discussion

PMI-RMP Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?


A.

Recommend the removal of risks to the project manager to reduce project risk exposure.


B.

Advise the client that the project has exhausted contingency.


C.

Quantify the risk exposure that exceeds project contingency.


D.

Generate reports to assess and communicate the project risk level.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.