Pre-Winter Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 37 Topic 4 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 37 Topic 4 Discussion

PMI-RMP Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?


A.

Risk mitigation


B.

Risk transfer


C.

Risk acceptance


D.

Risk avoidance


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.