PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 18 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 18 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?


A.

Confirm the risk triggers are still valid.


B.

Ask the architect to develop acceptance criteria.


C.

Review the feature with the project team.


D.

Escalate the issue to the project board.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.