PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 15 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 15 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?


A.

Avoid the risk


B.

Transfer the risk


C.

Ignore the risk


D.

Accept the risk


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.