PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 15 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 15 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

A risk manager is overseeing the construction of a new office building and finds that some risks were underestimated in their impact on the project timeline and budget. The risk manager is reassessing the current risk levels to prevent further escalation.

Which two actions should the risk manager take? Choose two.


A.

Conduct a detailed risk audit to verify the accuracy of the risk assessments.


B.

Implement automation to track project risks in real time.


C.

Adjust risk priorities in the risk register based on the new assessment data.


D.

Facilitate a risk-planning workshop to select strategies for the high-priority risks.


E.

Reassess risk exposure using predictive analytics tools.