Question #: 38
Topic #: 4

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?


A.

Evaluate any new risks that are introduced due to the change in scope.


B.

Update the risk management plan to reflect the scope change.


C.

Reassess the identified risks that impact the project scope.


D.

Update the risk register to identify, analyze, and plan a response for any new risk.