A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?


A.

Import a risk register from other industry chemical laboratories.


B.

Define chemical laboratory safety risk thresholds.


C.

Review published operational experience reports.


D.

Draft threat and opportunity risks that come to mind.