Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 8 Topic 1 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 8 Topic 1 Discussion

PMI-RMP Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team ' s approach to risk reports?


A.

Talk to the project team and ensure they avoid direct communication with this stakeholder.


B.

Engage with the team to enhance the project risk reports sent to the stakeholders.


C.

Highlight to the stakeholders the agreed predetermined frequency of risk reports.


D.

Work with the project sponsor to ensure stakeholders avoid directly influencing the project team.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.