PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 2 Topic 1 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 2 Topic 1 Discussion

PMI-RMP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?


A.

Risk description risk response, and quantitative data


B.

Project plan, risk complexity, and secondary risk


C.

Project plan, risk priority, and tool availability


D.

Risk description, risk probability, and risk impact 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.