Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 2 Topic 1 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 2 Topic 1 Discussion

PMI-RMP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?


A.

Close and communicate the results of the risk response actions.


B.

Run a workshop to analyze the effectiveness of the risk plan.


C.

Conduct a risk reserve analysis and document the results.


D.

Verify that all risk response actions have been documented. 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.