Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 2 Topic 1 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 2 Topic 1 Discussion

PMI-RMP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

What is an effect of adding the correlation to the model?


A.

Allows more risks to be included in the model.


B.

Reduces the project completion duration.


C.

Increases the standard deviation of the model.


D.

Increases the probability of correlated activities finishing on time.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.