Question #: 3
Topic #: 1

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders'?


A.

Monte Carlo analysis


B.

Pareto analysis


C.

Ishikawa analysis


D.

Qualitative risk analysis