PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 1 Topic 1 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 1 Topic 1 Discussion

PMI-RMP Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?


A.

Update the new risk in the risk register.


B.

Plan responses for the new risk.


C.

Passively accept the new risk.


D.

Add the new risk to the watch list.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.