PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 4 Topic 1 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 4 Topic 1 Discussion

PMI-RMP Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

in a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?


A.

Work breakdown structure (WBS)


B.

Affinity diagram


C.

Monte Carlo simul-ation


D.

Mind mapping


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.