Question #: 5
Topic #: 1

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?


A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis


B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis


C.

Decision tree analysis


D.

Cost-benefit analysis