PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 10 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 10 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?


A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.


B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.


C.

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.


D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.