PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 10 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 10 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?


A.

During the Plan Risk Management process


B.

Once all individual risks have been scored


C.

After risks have been identified by stakeholders


D.

Once the overall project risk has been estimated