Pre-Winter Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 31 Topic 4 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 31 Topic 4 Discussion

PMI-RMP Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?


A.

Add more float to the key activity


B.

Add more contingency to the project


C.

Review the plans for the key activity


D.

Increase the budget for the key activity


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.