New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 31 Topic 4 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 31 Topic 4 Discussion

PMI-RMP Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?


A.

Scenario-based risk analysis


B.

Quantitative risk analysis


C.

Qualitative risk analysis


D.

Monte Carlo analysis 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.